Programmed Works Details

Body: ESB

Legal Role: Electricity (Supply) Act, 1927 S.19 (b)
Administrative Role: Control, manage, and maintain in good repair and condition and proper and efficient working order each and every part or section of the Shannon works.
Physical Works: Annual cleaning of Kilmastulla River adjacent to Fort Henry Embankment (2.5km) and Black River and open drain (1km) adjacent to Ardclooney Embankment.
Permits/Licences: N/A
Assets: Fort Henry and Ardclooney Embankments (Category A)
Description: Fort Henry and Ardclooney embankments upstream of Parteen Weir. See attached map and GIS data.
Timing: Summer 2016
External Constraints: N/A
Output KPI: Approximately 3.5km of channels cleaned
Expected Outcome: Facilitates channel conveyance, reduces risk of localised flooding and protects Headrace Embankments